Hospital earthing, bonding and lightning protection

In a hospital, patients cannot be moved quickly, and the equipment that keeps them alive cannot tolerate even a few seconds of interruption. That is why standards place hospitals in the high-risk group in lightning risk assessment and set the strictest bonding rules for operating theatres and ICUs. We have worked alongside clients in more than 80 hospitals and healthcare centres across the country, from 64-bed buildings to large teaching hospitals and MRI earthing systems.

Anatomy of an incident

An official report on an incident at a hospital in Iran described this chain of events:

  1. 1. Lightning in the area
  2. 2. A fuse blew while the mains supply was still on
  3. 3. Emergency power and the UPS did not switch in on time
  4. 4. ICU equipment shut down

The lesson from this chain: protecting a hospital is not just an air terminal on the roof. Staged surge protective devices, bonding the emergency power supply to the same earthing system, and regular testing of the power changeover are part of it too.

The hospital, floor by floor

Each floor's colour shows its medical group: grey for Group 0 (no equipment contact with the patient), amber for Group 1 (external contact), red for Group 2 (operating theatre, ICU, angiography), blue for building services.

Roof and helipadLightning strike point

Roof, helipad, HVAC units and antennas

Tall hospitals with rooftop equipment are lightning's first target. Down conductors with long, winding routes draw the current into the building. In reports from hospitals in other countries, lightning striking the roof has caused power cuts, failure of operating theatre humidity control and the postponement of dozens of surgeries.

Our answer:
Lightning risk assessment, lightning protection system design coordinated with the helipad lights, and air rods with short, direct down conductors.
Operating theatre and ICUGroup 2

The patient is connected to equipment

In the operating theatre, the patient's body has lost its natural resistance. That is why the touch voltage limit is lower in these spaces, and every metal part in the patient environment, from the bed and IV stand to the medical gas pipes, must be connected by its own conductor to an equipotential bar in the same room. Daisy-chaining (from one device to the next) creates loops and puts noise on the ECG. These rooms also need a medical IT supply so that the first insulation fault does not cut the power.

Our answer:
Star-configured bonding and earthing design, accessible earth bars with every connection labelled, and bonding resistance testing at handover and periodically.
Inpatient wardsGroup 1

Patient rooms and nursing station

A Type AC residual current device cannot detect DC leakage from electronic medical equipment. Every bed also needs at least one bonding point.

Our answer:
An equipotential bar in every room and bonding continuity testing.
ImagingMRI and CT

MRI room

The RF enclosure of an MRI room is usually earthed at only one point, beside the filter panel. Any extra earth path through pipes, ducts or the quench pipe creates a loop and spoils image quality. The quality of the connection where pipes pass through the enclosure wall is critical.

Our answer:
Installing the MRI earthing system to the equipment maker's guidelines, with a single-point connection to the building earth. We have done this at Milad, Erfan and Pars hospitals.
Corridors and systemsGroup 0

Fire alarm, nurse call, cameras and network

The first things to burn out in a lightning strike are usually the low-current systems. That is because long cables between buildings and telecom lines come in unprotected.

Our answer:
Plant room and substationEmergency power

Diesel generator, UPS and main switchboard

A system meant to take over from mains power during an outage will itself be damaged, or fail to come online in time, if it is not coordinated with the lightning protection system.

Our answer:
Type 1 power surge protective devices (SPDs) at the intake, Type 2 and 3 at the emergency panels and UPS input, and connection of the generator and UPS to the same earthing system.
Below gradeEarth electrode

Earthing system and earth pits

The foundation for every floor above is one integrated earthing system with stable resistance, not several separate pits for different departments.

Reference: IEC 60364-7-710, IEC 62305-2 to 4, IEC 61643, IEEE 1100

Some of our projects

Major and teaching hospitals: the 1000-bed Milad Hospital, the 531-bed Bandar Abbas Mega Hospital, the 280-bed Shahid Rahnemoun Hospital in Yazd, a 273-bed hospital in Qaem Shahr, a 264-bed teaching hospital in Poldokhtar, a 220-bed teaching hospital in Semnan, Shariati, Amir Alam, Sina, Loghman Hakim, Shohada-ye Tajrish and the Children's Medical Centre

MRI earthing systems: Milad, Erfan and Pars hospitals

Provincial hospitals: Bushehr, Gorgan, Yasuj, Shahrekord, Urmia, Lahijan, Abhar, Baneh, Nahavand, Sirjan, Piranshahr, Naqadeh, Abadan, Tonekabon and dozens of other cities

Outside Iran: Imam Ali Hospital, Najaf

What to send for design and a quotation

Architectural drawings showing the use of each space (group 0, 1 or 2), single-line diagrams of normal and emergency power, the location of generators and UPS, rooftop equipment and the helipad, and for MRI, the equipment maker's installation guide.

Frequently Asked Questions

Why does an operating theatre need its own bonding?

Because the patient is connected to equipment and the body has lost its natural resistance, even a small voltage between two metal parts is dangerous. Bonding every metal part to a single bar in the same room removes this voltage difference.

Can a hospital UPS take the place of an SPD?

No. A UPS is there for power cuts. Its bypass path carries the surge straight to the load. SPDs must be installed upstream of the UPS and on the bypass path.

Is MRI earthing the same as the building earthing?

The MRI enclosure is connected to the building earthing system at a single point and must have no other earth path. The details are set by the equipment maker's installation guide.

Have a Technical Question?

KALOT Group's technical experts are ready to answer your questions about lightning rods and earthing systems.