Nikan Accident and Burn Hospital
- Location:
- Tehran
On the Nikan Accident and Burn Hospital project, KALOT Group installed four separate down conductor routes on different parts of the building facade. Working from a cradle at height, our installation team reached the facade and fitted the routes in straight, orderly runs with continuous fixings. The photos from this stage show the conductor details on the facade and the routes on the roof. Work will continue once the project's remaining infrastructure is ready.
nikan-hospital-facade-conductor-video.mp4The main challenge at this stage was installing four down conductor routes accurately on the building's tall facade and keeping them true and aligned throughout the work. Working from a cradle gave the team access and allowed the conductor and clamps to be fixed in an orderly way. The parts that depend on infrastructure not yet ready will be completed in the next stage.
Have a Technical Question?
KALOT Group's technical experts are ready to answer your questions about lightning rods and earthing systems.